DTC

  • Increase font size
  • Default font size
  • Decrease font size
dtc_banner7.jpg
Home Projects
Projects

Central Artery Tunnel Inspections, Boston

E-mail Print PDF

photo_projects_centralarteryOn July 10, 2006, a section of suspending ceiling panels in Boston’s I-90 Eastbound Connector Tunnel collapsed onto live traffic tragically killing a local woman. The Connector Tunnel is part of Boston’s “Big Dig” tunnel network, formerly known as the Central Artery/Third Harbor Tunnel (CA/T) project, which was being operated and maintained by the Massachusetts Turnpike Authority. Following the collapse, then Governor Romney took control of the investigation ordering the Executive Office of Transportation (EOT) to perform and oversee an independent evaluation of the tunnel’s condition.

On July 25, 2006, DTC was hired by the EOT under the direction of the Massachusetts Highway Department (MHD) to perform emergency safety inspections of the CA/T tunnel system. Work began immediately, when DTC mobilized staff the next evening to inspect anchorage systems for two large air-circulatory jet fans located in Ramp F, one of the connector tunnels. 

Since that initial assignment, work continued at a brisk pace where DTC conducted in-depth inspections on miles of other CA/T connector and main line tunnel sections, including the I-90 Westbound Connector Tunnel, Ramp B, Ramp L, Ramps D & DN, and Ramp RT. 

The inspections originally focused on the ceiling panel anchorage support systems and quickly developed into the full inspection and assessment of all of the tunnel elements including the development, with EOT/MHD, of inspection procedures and specific inspection report forms to be used by all consultants. The Inspected items included ceiling panel hanger units, roof slabs, roadways and safety walk areas, tunnel finishes and false walls, slurry walls, wall and roadway plenums, and utilities. 

Immediately following each inspection, DTC prepared report summaries and deficiency reports with recommendations for each deficient item. DTC is in the process of preparing formal inspection reports.

 

Barnum East End Elementary School

E-mail Print PDF

photo_projects_barnumDTC, in conjunction with JCJ Architecture, is performing complete engineering services for the construction of a new Pre-K through eighth grade elementary school. Services include: environmental site investigation, analysis and remediation planning, site layout and vehicular circulation; landscaping and site lighting; extension and/or relocation of site utilities such as: water distribution, sanitary sewer system, storm sewer system and electric /communication/ cable television/ gas; permitting; structural design and HVAC and fire protection design.

 

Slater Hill Bridge Replacement

E-mail Print PDF
killingly01DTC was contracted by the Town of Killingly to design a bridge replacement for a single span bridge over Slater Brook. The existing bridge was closed after an inspection revealed undermining and failure of one of the abutments. The newly constructed bridge consists of a precast arch spanning 12 feet over Slater Brook along with 20 foot high wing walls. DTC was also responsible for performing the hydraulic analysis and obtaining all permits required as part of the State’s Local Bridge Program.
 

State Street Bridge Reconstruction

E-mail Print PDF

State Street BridgeThis project, designed by DTC, is currently under construction and DTC is providing the Construction Phase Services. Funding is provided under the STP-Urban Program. The project involves replacing the existing two span concrete bridge with a single 80 foot span comprised of pre-stressed bulb-tee beams with a concrete deck supported by cantilevered abutments on concrete filled steel pipe piles. The bridge carries State Street over the Mill River, and one end of the bridge is under another bridge carrying Interstate 91. Two lanes of traffic must be maintained during the two stages of construction.

The challenges DTC resolved included installing new piles, and support of excavation, adjacent to the I-91 overhead bridge pier footing which is also founded on piles. The solution involved a combination of splicing piles and sheeting with shorter length units and re-adjusting locations in addition to requiring on-site testing and monitoring. As part of the design process, DTC also performed a detailed hydraulic analysis and scour assessment for this project. Considerable tidal influence severely affected flows through the existing bridge that caused scour issues to develop with the existing pile supported bridge foundation. A proposed bridge pile support system and riprap scour protection were recommended to protect the proposed bridge from further scour issues. DTC's hydraulic and scour analysis became an integral part of the Flood Management Certification process required for this project.

 

Massachusetts Turnpike Authority (MTA) GEC

E-mail Print PDF

MTA GECAs a subconsultant to two firms, DTC has been providing tunnel and bridge inspection services on the following General Engineering Consulting Services Contracts:

  • To date, DTC has performed hands-on tunnel inspections in the TWT (Ted Williams Tunnel) and I-93 SB (southbound) Tunnels as well as culvert inspections along I-90 from Rte. 128 to the New York Border.
  • To date, DTC has performed in-depth inspections on the Zakim Bridge and the CA/T north side connector loop ramps, and portions of I-90 over the CSX Yard.  Structure types included steel box girders, prestressed concrete box girders, CIP post-tensioned box girders, and steel stingers structural systems.
  • To date, DTC has performed hands-on tunnel inspections in the TWT.
 


Page 19 of 22